Subgrade preparation underway
Earthwork, grading, water main and storm sewer were complete; subgrade and subdrain work had begun in preparation for paving.
Source
Road and utilities serving Allied Construction Services development.
Mapped street context. The highlighted road is not the project’s contract boundary; see the project limits below.
Original map: WDM Development. Road and water geometry: U.S. Census Bureau. Responsive WebP copy.View original sourceRoad and utilities serving Allied Construction Services development.
Earthwork, grading, water main and storm sewer were complete; subgrade and subdrain work had begun in preparation for paving.
SourceOfficial records and reporting, with access limitations noted.