West Des Moines Development
Dates and segments matter

Roadwork & infrastructure

Dated source reports, not live traffic. Check the responsible agency before traveling; a completed segment does not mean the whole road is open.

Check the city’s current updates ↗
Source dated 2026-10-30

Mills Civic Parkway and S. 95th Street

Immediately west and south of Woodland Hills Community Church, 33365 335th Street, Waukee

County said closures would remain on Nov. 3: Mills Civic west of site and S. 95th south; approach from east, both parking drives open. Precinct 224 polling place.

Opening or target in source
November 3 election-day advisory, not a live traffic feed
Current-condition limit
County advisory applicable 2026-11-03; no newer superseding notice found

Date-specific advisory for 2026-11-03

Original dated update ↗
Source dated 2026-09-10

Booneville Road

S. 60th Street approximately 1,200 feet east toward Raccoon River

Paving complete; road remained closed during cleanup and restoration

Opening or target in source
Not verified
Current-condition limit
not verified
Original dated update ↗
Source dated 2026-09-10

Grand Avenue

I-35–S. 60th Street

Westbound reopening September 11 was a future target in source, not observed completion

Opening or target in source
2026-09-11 prospective
Current-condition limit
not verified
Original dated update ↗
Source dated 2026-09-10

16th Street and Grand Avenue

16th Street intersection

Intersection closed; Grand Avenue maintained one lane each direction

Opening or target in source
Spring 2027 target
Current-condition limit
not verified
Original dated update ↗
Source dated 2026-09-10

Grand Avenue widening

S. Jordan Creek Parkway–S. 60th Street

Grading and sewer underway

Opening or target in source
Summer 2027 target
Current-condition limit
not verified
Original dated update ↗
Source dated 2026-08-26

Ashworth Road

19th–23rd Street

Through closure 19th–22nd reported

Opening or target in source
Spring 2027 target
Current-condition limit
not verified
Original dated update ↗
Source dated 2026-08-26

Mills Civic Parkway

S. 81st–S. 88th Street

Substantially complete

Opening or target in source
Not verified
Current-condition limit
not verified
Original dated update ↗
Source dated 2026-08-18

EP True Parkway

Wendover Lane–S. Grand Prairie Parkway

Opened August 17; punch-list work remained

Opening or target in source
Opened 2026-08-17
Current-condition limit
not verified
Original dated update ↗
Source dated 2026-08-12

Mills Civic Parkway

S. 91st Street–S. Grand Prairie Parkway

Road closed; second phase underway

Opening or target in source
Not verified
Current-condition limit
not verified
Original dated update ↗
Coverage and access

City entries use dated indexed source text where the full page was unavailable during review. Historical closures are not labeled as current closures. The county’s election-day notice applies to November 3, 2026 and the precise polling-place approaches described, not all of Mills Civic Parkway. This list is not every work zone in the city.

Evidence reviewed 2026-11-03.