West Des Moines Development
← Projects

Water-main renewal

Multiple construction phases

Replacement and road-linked water work renews the local distribution network across established neighborhoods and growth corridors.

Project images and plans

Service area
Citywide water networkSource
Program stage
Multiple construction phasesSource
Source period
October 14, 2026Source

Projects & phases

S. 35th Street replacement
Seeding finished; acceptance expected by year-end.Source
Pheasant Ridge replacement
Preparatory work begun.Source
Railroad Avenue replacement
Construction began the week of October 12.Source
Ashworth Road, 19th–23rd
Final connections approaching; overall road project ongoing.Source
Grand Avenue, I-35–S. 60th
Water work complete; acceptance pending the overall city project.Source
Grand Prairie / E.P. True intersection
Water work complete; overall project acceptance pending.Source
E.P. True: Grand Prairie–Bridgewood
Water work complete; overall project acceptance pending.Source
E.P. True: Bridgewood–Wendover
Water work complete; overall project acceptance pending.Source
Giles Street 2025 and 2026
Water components complete; overall project acceptance pending.Source
SE 35th Street extension
Completed work; acceptance communication in the May 20, 2026 packet.Source
Blue Creek water-main encasement
Work completed in April report; formal closeout not verified.Source
2026 valve replacement
April 15 proceedings record acceptance of the completed replacement project.Source
Grand Avenue: S.88th to Grand Prairie
City accepted the road-linked water improvements June 16, 2025, according to Water Works' October 2025 communication.Source
Ashworth Phase 4 and Stagecoach S.78th–S.81st
Completed road-linked water work listed for acceptance in the October 15, 2025 packet; final Water Works vote not independently checked.Source
Mills Civic/S.35th and Veterans Parkway water work
2025 main replacement and extension projects listed as completed for acceptance in the November 17, 2025 packet.Source

What matters next

Program status
Multiple construction phases.Source
Next milestone
Updated agency schedules, adopted capital plans and phase-completion notices.
Project context

Replacement and road-linked water work renews the local distribution network across established neighborhoods and growth corridors.

Project milestones

Documented program stage

Replacement and road-linked water work renews the local distribution network across established neighborhoods and growth corridors.

Source

Documents & sources

Official records and reporting, with access limitations noted.

Open questions

Explore another project

Grand Experience →Valley West Mall →RecPlex Event Center →Microsoft campuses →All city projects →